The project was a 2-strand continuous billet casting facility with a production output capacity of 108,000 MT per year. Fildravo provided detailed engineering design and construction management services for the following:
- Concrete building foundation and its superstructure.
- Concrete foundation for equipment.
- Water treatment plant building, including tanks, pumps, and equipment foundations.
- Generator foundations and substation.
- Elevated cooling water tank.
- Facility drainage system.
- Piping system for cooling water and all utility lines.
- Ductwork and exhaust system.
- Electric systems for equipment lighting, instrumentation, and controls.
Detailed Engineering Design
- Structural Design
- Foundation Design
- Sanitary Design
- Electrical Design
- Mechanical Design
- Preparation of Design Reports
- Preparation of Contract Drawings and Technical Specifications
- Preparation of Bill of Quantities (BOQ) and Cost Estimates
Construction Supervision
- Pre-Construction/Tendering Stage
- Construction Stage
- Post Construction